HIGHLIGHTS

 

Nodal Agency

Rajasthan Renewable Energy Corporation Limited (RREC)

Targets

Particulars

Capacity

Hybridisation of existing Wind/Solar plants

200 MW

New Wind-Solar Hybrid Projects

2000 MW

Wind-Solar Hybrid with storage systems

500 MW

Hybridisation of existing Conventional plants

800 MW

Target to be achieved before FY 2024-25

Wind Power Project

  • Sale of power to DISCOM/RUVNL using competitive bidding mechanism facility to power developer.
  • Power developer is eligible for sale of non-solar certificate.
  • For captive use, power plant capacity cannot exceed contract demand. In case of third party sale by power plant, the capacity cap is removed.

Wind Power Plant with Storage

  •  DISCOM will purchase a minimum 5% of RPO target (in terms of capacity MW) from wind storage project.
  • Minimum capacity of storage system must be half of installed capacity of the wind project.

Repowering of Wind Power Project

  • Repowering of plants more than 10 years of age.
  • After repowering, the power generated, equivalent to average of the last 3 years, will be procured according to PPA, and the additional power will be purchased at the competitive bidding rate.
  • Load flow study will be provided by DISCOM/RVPN.

Third Party/Captive use

  • For captive use and third party sale, agreement for wheeling and banking must be signed with DISCOM.
  • For transmission, agreement with RVPN is required.

Allotment/Procurement of Land

Government Land

  • Allotment will be made as per Rajasthan Land Revenue (Allotment of land for setting of power plant based on RE sources) Rules 2007, as amended from time to time.
  • Land will be allotted against security deposit of Rs.1 Lakh/MW in favour of RREC.
  • Security deposit will be forfeited in case the allotted land is not used within the specified period as mentioned in the allotment rules.

Private Land

  • Developers will be allowed to set up hybrid power plants on private agricultural land without requiring land conversion.
  • Developers will also be used to acquire/hold private land in excess of ceiling limits from title holders for setting up of hybrid power plant.
  • Stamp duty on land used for hybrid power plant will be twice that for agricultural land in the same area.

Registration of Wind Power Project

  • Developers and power producers need to pay the following charges:

For projects

Rs.50,000/MW

For projects ≥ 100 MW

Rs.5 million/project

  • GST and other charges will be applicable. Registration will not confer rights to the applicant.
  • Developer/power producer can transfer registration or part thereof to ‘holding’, ‘subsidiary’, ‘fellow subsidiary’ and ‘ultimate holding’ company with permission from RREC.

In-Principle Clearance

Project clearance is based on Committee examining:

  • Detailed project report.
  • Financial capability of the power producer.
  • Availability of power evacuation system for proposed project.
  • PPA agreement between energy producer and consumer.

 

OTHER PROVISIONS

 

Incentives to  Wind Equipment Manufacturers

  • Land allotted at 50% concession.
  • Full exemption on stamp duty and electricity duty.
  • SGST subsidy and employment subsidy.

Hybridisation of Thermal Power Plant

  • Setting up of RE plants will be permitted.
  • Power from RE plants can be used to meet scheduled generation of thermal power plant.
  • Any gain from sale of RE power must be shared with DISCOM.

Registration Fees

Project Capacity

Fees

Less than 10 MW

Rs.5000/MW

From 10 MW up to ≤ 50 MW

Rs.0.5 million

From 50 MW up to 100 MW

Rs.1 million

Over 100 MW

Rs.3 million

Allotment of Land for Wind-Solar Hybrid plants

Technology

Maximum Area

SPV on crystalline technology

3 hectare/MW

SPV with tracker

3.5 hectare/MW

SPV with thin film/amorphous

3.5 hectare/MW

Rajasthan Renewable Energy Development Fund

  • Specified charges will be paid by the producer for up-gradation and maintenance of grid. Charges will be paid for the entire lifetime of the project. Fees will be paid according to installed solar capacity.

Projects commissioned up to 31.03.2024

Rs.0.2 million/MW/year

Project commissioned from 1.4.2024 to 31.03.2025

Rs.0.3 million/MW/year

Projects commissioned from 1.4.2025 to 31.03.2026

Rs.0.4 million/MW/year

Projects commissioned on/after 1.4.2026

Rs.0.5 million/MW/year

  • Bids before commencement of policy will be charged at Rs.0.1milllion/MW/year.
  • Contribution is waived off for sale of power to DISCOMs and for captive consumption.

Incentives and Facilities for Captive use or Third Party Sale

  • Electricity banking facility on yearly basis.
  • Exemption from electricity duty.
  • Transmission and wheeling charges:
    • For intra-state. transmission @ 50%
      • For inter-state, @ 25% of Commission approved charges.

Agency for Grid Integration and Power Evacuation

Rajasthan Rajya Vidyut Prasaran Nigam Ltd (RVPN) and local distribution company.

Link

https://energy.rajasthan.gov.in/content/raj/energy-department/rrecl/en/home.html#

About Portal

‘All About Renewables’ aims to bring about a change in the way we ‘look and search’ for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

(020) 26613855
(020) 26613832