Download Home Back

Karnataka Solar Policy — 2014 (3rd Amendment)

HIGHLIGHTS

 

Nodal Agency

Karnataka Renewable Energy Development Ltd (KREDL).

Applicable Technologies

Solar PV, solar rooftop, solar thermal, canal-top, solar pump sets, solar-renewable hybrid projects.

Policy Period

2014-2021

Targets under Policy

  • Capacity addition of 6000 MW including 2400 MW from rooftop projects by 2021.
  • Promotion of investment in solar industry and enhanced employment opportunities.
  • Introduction of inter-state open access model and energy banking.
  • Wind-solar hybrid technology.

Eligible Entities

 

  • Any individual.
  • Any firm/society/institution/registered company.
  • Residential/commercial/govt./building owners.

Policy Evaluation

After study in FY 2019-20, suitable amendments will be given.

Tax Exemption

Not available.

Evacuation Arrangement

Shall be borne by the developer as per CEA regulations.

Fees and Charges  (Rs.)

Category

Application Fees (per project)

Facilitation Fee

Deposit/    MW

Net worth/ MW

Competitive bidding

10,000

100,000/MW

10,00,000

30% of capital cost

REC (Supply at APPC)

10,000

20,000/MW

5,00,000

50,00,000

Captive/Group captive

10,000

25,000/MW

5,00,000

30% of capital cost

IPP for sale

10,000

25,000/MW

5,00,000

30% of capital cost

Solar park on wasteland

1,00,000

25,000/MW

0

2,00,00,000

Bundled power

10,000

10,000/MW

0

0

Rooftop (5 to 50 kW)

1,000

2,000/project

0

0

Rooftop (51 to 1000 kW)

2,000

5,000/project

0

0

 

OTHER PROVISIONS

 

RPO Target

Year

2014-15

2015-16

2016-17

2017-18

2018-19

2019-20

2020-21

Solar RPO as % of total consumption of energy

1.5

 

1.75

2.0

 

2.25

 

2.5

 

2.75

 

3

 

Category of Solar Projects

 

  • Category 1: Removed in the amendment.
  • Category 2: Projects based on competitive bidding for capacities more than 3 MW will be selected based on two categories: those availing AD benefits and those not availing AD benefits. The minimum capacity allocation for grid-connected plants will be 3 MW for solar PV and 10 MW for solar thermal.
  • Category 3: Projects under REC Mechanism – Developer can sell electricity to ESCOMs at APPC, as determined by KERC. Minimum capacity allocation is 1 MW for solar PV and 10 MW for solar thermal. Maximum allocation is limited to transmission capacity.
  • Category 4: Projects under captive/group captive generation will have no limit on the minimum and maximum project allocation. The wheeling, banking charges and cross-subsidy surcharge are applicable as per KERC guidelines.
  • Category 5: Projects under IPPs – Minimum capacity is 1 MW for solar PV and 10 MW for solar thermal.

Projects under bundled power – The state encourages central/state PSUs and government-initiated power exchanges to set up solar power projects for providing solar power bundled with thermal power from outside the state at rates determined by the govt., subject to approval by CERC/KERC. The capacity allocations under this category are based on the bundled tariff agreed with the power purchaser.

Net Metering

  • The state govt. shall encourage grid-tied, building-integrated, PV based, building architecture. ESCOMs to issue specific guidelines for connectivity of rooftop projects to the network. Project capacity is restricted by regulations issued by KERC.
  • Gross metering service is available for solar rooftop only. Energy injected into the grid will be compensated on rate fixed by KERC.
  • Wind-solar hybrid projects are promoted to rooftop sector.

Solar off-grid and Decentralized Distributed Generation (DDG):

 

  • State govt. encourages solar street lights (through local bodies) and rooftop SPV systems with battery storage, in rural and urban areas, so as to reduce the dependency on the grid.
  • Solar powered pump sets – Since irrigation pump sets in Karnataka consume about one third of the total energy, the use of solar powered pump sets will reduce burden on the grid.

Other Initiatives

 

  • Development of solar parks – Utilizing waste lands for development of solar parks in off-grid and grid-connected mode. Size of solar park is limited to 100 MW per taluka. Minimum size of private solar parks to be 25 MW.
  • Grid-tied canal corridor projects – State shall support such projects by the irrigation department subject to purchase of energy by ESCOMs.
  • Grid-connected “solar with other renewable hybrid projects” – State shall promote solar projects with other renewable sources, provided a minimum of 25% of overall generation comes from the respective sources.

Fiscal Incentives

 

  • MNRE provides concessions such as Central Financial Assistance, concessional customs duty on specified items, excise duty and sales tax exemption, tax holidays etc.
  • Tax concessions by the state govt. on entry tax, stamp duty and registration charges according to industrial policy.

Change of category by solar plant 

IPP and captive/group captive can change to solar park category but bank guarantee will not be returned.

Links

 

http://kredlinfo.in/solargrid/Solar%20Policy%202014-2021.pdf

 

References

 

(1st amendment)

nd amendment) 

(3rd amendment)

 

 

About Portal

‘All About Renewables’ aims to bring about a change in the way we ‘look and search’ for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

(020) 26613855
(020) 26613832