Eligibility Conditions  

  • Consumer should be in the supply area of the distribution licensee.
  • Plant capacity should not be more than 80% of sanctioned connected load.
  • Minimum plant capacity should be more than 1 kWp and maximum 1 MWp.

 

Capacity Target for Distribution Licensee

Cumulative capacity should be restricted to 30% of the rated capacity of the respective distribution transformer.

 

Metering Arrangement

  • Bi-directional meter will be installed at the interconnection point with the network of the distribution licensee.
  • Existing meters of consumers would be replaced by net meters.
  • Check meters are mandatory for systems having capacity of more than 250 kW but optional otherwise.

 

 

OTHER PROVISIONS

 

Energy Accounting and Settlement

  • Domestic category consumers where electricity injected exceeds electricity consumed:
    • Electricity injected up to 100 units will be adjusted in the next billing period.
    • Excess electricity injected above 100 units will be paid @ Rs.3.14/unit.
    • Capping of the average generation of 4.8 units per kW of the approved installed capacity per day of the rooftop solar PV system will be applicable.
    • For non-domestic consumers a cap of 4.8 units per kW/day of approved installed capacity is applicable. Excess energy injected will not be compensated.
    • If a consumer leaves the system, the excess energy credit shall lapse and no reimbursement will be given.

 

Other Charges

Exemption from banking and wheeling charges and cross-subsidy surcharge.

 

Penalty

As decided by the Commission from time to time.

 

Links

http://rerc.rajasthan.gov.in/

 

Reference

http://rerc.rajasthan.gov.in/Regulations/Order84.pdf http://rerc.rajasthan.gov.in/Regulations/Reg113.pdf

 

 

About Portal

‘All About Renewables’ aims to bring about a change in the way we ‘look and search’ for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

(020) 26613855
(020) 26613832