Download Home Back

Karnataka Renewable Energy Tariff Orders*

HIGHLIGHTS

 

Tariff Period

Technology

Years

Wind

Not available

Mini-hydel

Not available

Bagasse based cogeneration

Not available

Rankine cycle based biomass (water cooled condenser).

Not available

Solar rooftop and small PV power plants, grid-connected megawatt-scale solar power plants.

25

 

 

Control Period

Technology

Years

Wind

5 years from October 10, 2013

Mini-hydel, bagasse based cogeneration, Rankine cycle based biomass (water cooled condenser).

Up to 31.03.2018

Solar rooftop and small PV power plants, grid-connected megawatt-scale solar power plants.

5 years from April 1, 2013

 

 

Useful Life of a Plant

Technology

Years

Wind, solar rooftop and small PV power plants, grid-connected megawatt-scale solar power plants.

25

Mini-hydel

35

Bagasse based cogeneration, Rankine cycle based biomass (water cooled condenser).

20

 

 

Technology-wise Gross Tariff

Technology

Gross Tariff

(in Rs./kWh)

Wind

4.50

Mini-hydel

4.16

Bagasse based cogeneration Fixed cost:2.02

Variable cost (FY 2016-17):2.97

Rankine cycle based biomass (water cooled condenser). Fixed cost:2.37

Variable cost (FY 2016-17): 2.98

Solar rooftop and small PV power plants Without Capital Subsidy
1 to 10 kW

7.08

Above 10 kW and up to 50 kW

6.61

Above 50 kW and up to 100 kW

6.14

Above 100 kW and up to 500 kW

5.67

Above 500 kW and up to 1 MW

5.20

With Capital Subsidy of 15%
1 to 10 kW

6.03

Above 10 kW and up to 50 kW

5.63

Above 50 kW and up to 100 kW

5.23

Above 100 kW and up to 500 kW

4.83

Above 500 kW and up to 1 MW

4.43

Grid-connected megawatt-scale solar power plants Solar PV

6.51

Solar thermal

10.85

 
Capital Cost

Technology

Capital Cost

(in Rs. lakh/MW)

Wind

600.00

Mini-hydel

620.00

Bagasse based cogeneration.

475.00

Rankine cycle based biomass

570.00

Solar rooftop and small PV power plants.

*505.02

Grid-connected megawatt-scale solar PV plants.

600.00

Grid-connected megawatt-scale solar thermal plants.

1200.00

*Excluding land cost
Operation and Maintenance (O&M) Expenses

Technology

O&M Cost (in Rs. lakh/MW) for the base year

Wind

9.51

Mini-hydel

12.40

Bagasse based cogeneration

14.25

Rankine cycle based biomass

30.00

Solar roof top and small PV power plants.

5.05

Grid-connected megawatt-scale solar PV plants.

13.00

Grid-connected megawatt-scale solar thermal plants.

17.72

An annual escalation at the rate of 5.72% shall be considered.

Interest Rate on Loans

  • 12% for solar rooftop PV and small solar plants.
  • 12.5% for other technologies.
Depreciation

5.83% for first 12 years and remaining depreciation spread over the residualuseful life of the project.

Return on Equity

16%

Interest on Working Capital
  • 13.25% for megawatt-scale solar power plants, mini hydel, bagasse based cogeneration and Rankine cycle based biomass power plants.
  • 13% for wind power plants.
  • 12.5% for solar rooftop and small solar PV plants.

 

OTHER PROVISIONS

 

Tariff Structure and Design

Generic, single part, levellised tariff.

Merit Order Despatch Principle

All renewable energy projects are treated as ‘Must Run’ power plants.

Subsidy or/and incentives by government Not available
Rebate Not available
Late payment surcharge Not available
Links http://www.karnataka.gov.in/kerc/Pages/Generic%20Tariff%20Orders.aspx
References http://www.karnataka.gov.in/kercold/Downloads/COURT-ORDERS-2016/TARIFF_FY-17/Solar_Tariff_2016/Solar_Rooftop_Photovoltaic_Tariff-ORDER-dated-02.05.2016.pdf

http://kredlinfo.in/solargrid/Determination_of_tariff_for_Grid_Interactive_Megawatt_scale_Solar_Power_Plants.pdf

http://www.karnataka.gov.in/kercold/Downloads/COURT-ORDERS-2015/ORDER-Revised_Wind_Tariff_Order-%2024.02.2015.pdf

http://www.karnataka.gov.in/kercold/Downloads/COURT-ORDERS-2015/FinalREOrder1.1.2015.pdf


Provisions for Gross Metering/Net Metering

 

Installed Capacity
  • Not less than 1 kw and not more than 1 MW shall be allowed subject to further limit based on the sanctioned load of the consumer’s installation.
    • Cumulative capacity of SRTPV plants should not exceed total capacity of the state
Implementation and Reporting Procedure
  • Upon receiving approval from distribution licensee the eligible consumer shall enter into a PPA with the distribution licensee within 15 days from receipt of the approval subject to further approval from the commission.
  • If eligible consumer fails to commission SRTPV plant within 6 months of the approval of PPA the applicable tariff for the SRTPV shall be agreed tariff or any revised tariff or APPC prevailing on date of commissioning, whichever is lower.
Interconnection Clauses
  • Connectivity level for SRTPV plants for connecting to the distribution network shall be as follows –

Installed Capacity

Voltage Level

Upto 5 Kw

230V – single phase

Above 5 Kw and up to 50 Kw

400V – three phase

Above 50 Kw and up to 1000 Kw

11 Kv HT

  • Connectivity norms are applicable for all type of consumers.
  • EHT/HT consumers may install system at LT/HT voltage.
  • In case of gross metering exclusive line shall be laid from SRTPV to distribution system.
  • The cost of distribution network up to the interconnection point shall be borne by the consumer.
Capacity Limit for Distribution Transformer
  • Total capacity of the existing and proposed SRTPV plants below 50 Kw capacity connected to the existing distribution transformer through which electricity is supplied to the consumer shall not exceed 65% of rated capacity.
  • Total line current of the existing and proposed SRTPV plants above 50 Kw connected to the existing 11 Kv distribution system shall not exceed 65% of the rated carrying current capacity of that line.
Safety Aspect
  • Eligible consumer will be responsible for safe operation, maintenance and rectification of defects of SRTPV system up to interconnection point
  • Distribution licensee will be responsible for safe operation, maintenance and rectification of defects in the distribution system beyond distribution line 
Metering System
  • As per standards set by CEA (Installation and Operation of meters) Regulations, 2006
  • For gross metering, bi-directional meter shall be installed at the interconnection point with the distribution network.
  • For net metering, the existing consumer meter shall be replaced with the bi-directional meter having the facility of downloading meter reading using meter reading instruments (MRI) and the cost of new or additional meter shall be borne by the consumer and installed by the distribution licensee.
Energy Accounting and Settlement
  • Meter reading shall be taken monthly basis or as per billing cycle specified in the electricity supply code.
  • The licensee shall show electricity exported by the consumer during a period for gross metering.
  • In case of gross metering, if any import of energy is measured, the same shall be billed at the rate which is higher of the (i) tariff agreed to in the PPA (ii) prevailing retail supply tariff applicable to the category of the installation of the eligible consumer.
  • In case of net metering the licensee shall show in the bill separately the quantum of electricity injected by the eligible consumer, quantum of electricity supplied by the licensee to the consumer and the net electricity billed for payment by the consumer during the given billing period provided that
    • excess electricity injected to the distribution network shall be paid by the distribution licensee as per tariff agreed in the PPA.
    • excess electricity supplied to the consumer’s system by the distribution licensee shall be billed by the distribution licensee as net electricity consumption by the consumer at the tariff applicable to such consumer.
PPA
  • PPAs for plants with below 500 Kw installed capacity shall be deemed to be approved by the commission on the date of its execution by the parties
  • Approval for PPAs signed for plants with capacity 500 Kw  and above shall be sought from the commission by the distribution licensee within seven days from the date of signing the PPA.
Reference

http://www.karnataka.gov.in/kerc/Regulations/Draft%20Regulations/Implementation_of_SRPTV.pdf

 

  • Karnataka does not have technology wise regulations. Data from different orders has been compiled in this summary

 

 

About Portal

‘All About Renewables’ aims to bring about a change in the way we ‘look and search’ for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

(020) 26613855
(020) 26613832