Download Home Back

Himachal Pradesh (Promotion of Generation from Renewable Energy Sources, and Terms and Conditions for Tariff Determination) Regulations, 2017

HIGHLIGHTS

 

Tariff Period

Technology

No. of Years

Non-fossil fuel based co-generation, biomass based on Rankine cycle, biomass gasifier, biogas, wind, solar thermal, and any other renewable energy technology approved by MNRE.

As may be fixed by the Commission

Solar PV

25

Small hydro

40

 
Control Period

From 1st October 2017 to 31st March 2020 unless reviewed earlier or extended by the Commission.

Useful Life of a Plant

Technology

No. of Years

Non-fossil fuel based co-generation, biomass, municipal solid waste (MSW)/refuse derived fuel (RDF) based power projects.

20

Wind, solar PV, solar thermal

25

Small hydro

40

Any other RE technology approved by MNRE.

As may be fixed by the Commission

 
Technology-wise Net Tariff

 

Technology

Net Tariff (Rs./kWh)

Solar PV projects up to 1 MW (for projects commissioned between 01.04.2017 and 30.09.2017)†

4.37

Solar PV projects between 1 MW and 5 MW (for projects commissioned between 01.04.2017 and 30.09.2017) †

4.31

Solar PV projects up to 1 MW (for projects commissioned between 01.10.2017 and 31.03.2018)*

4.31

Solar PV projects between 1 MW and 5 MW (for projects commissioned between 01.10.2017 and 31.03.2018)*

4.25

Small Hydro (above 100 kW and up to 2 MW)

3.79

Small Hydro (above 2 MW and up to 5 MW)

3.61

Small Hydro (above 5 MW and up to 25 MW)

3.44

  • Generic levelised tariff will be determined in the following cases:
  • For small hydro projects which were:
    • commissioned on or after 1st January 2015 and
    • have no PPA approved by the Commission before the date of commencement of these regulations
    • have no joint petition for approval of PPA before the Commission
    • have not commenced operations prior to the date of commencement of these regulations.
  • SHP projects covered by the above clauses shall adopt either project specific or generic levelised tariffs, or any mutually agreed tariff, or a tariff determined by competitive bidding.
  • RE technologies other than SHP and SPV shall adopt:

    • either generic levelised tariff at Commission determined terms and conditions issued from time to time, or

    • project specific tariff at the time of jointly applying for PPA, or

    • tariff discovered through competitive bidding following Commission determined terms and conditions.
Capital Cost All capital costs are for FY 2017-18. For subsequent years the capital cost is determined using indexation formula given in Regulations.

Technology

Capital Cost

(in Rs.lakh/MW)

Solar PV projects up to 1 MW (for projects commissioned between 01.04.2017 and 31.03.2018)

452.70

Solar PV projects up between 1 MW and 5 MW (for projects commissioned between 01.04.2017 and 31.03.2018)

446.00

Small hydro projects above 100 kW and up to 2 MW

880.00

Small hydro projects above 2 MW and up to 5 MW

850.00

Small hydro projects above 5 MW and up to 25 MW

800.00

 

·         For all other technologies, the capital cost is determined by the Commission from time to time.

Operation and Maintenance (O&M)Expenses

Technology

O&M Cost

(in Rs. Lakh/MW)

FY 2017-18

Solar PV projects

7.40

Small hydro projects above 100 kW and up to 2 MW

33.00

Small hydro projects above 2 MW and up to 5 MW

29.00

Small hydro projects above 5 MW and up to 25 MW

24.00

For all other technologies – as stipulated in relevant orders of the Commission.

O&M cost shall be escalated @ 5.72% per annum.

Capacity Utilization Factor

  • 55% for all SHP projects.
  • 19% for SPV projects.

  • As stipulated in relevant orders of the Commission for other technologies.

Auxiliary Consumption

  • 1% of gross generation for SHP projects.
  • As stipulated in relevant orders of the Commission for other technologies.

Free Power by SHP Projects

S. No.

Category of Small Hydro Project

Free Power Structure

1

Above 100 kW and up to 2 MW

3% for the first 12 years and 13% for the remaining 28 years.

2

Above 2 MW and up to 5 MW

7% for the first 12 years and 13% for the remaining years.

3

Above 5 MW and up to 25 MW

13% for the entire tariff period of 40 years

 

Energy Losses

0.7% of net generation. 

Interest Rate on Loans
  • For solar PV projects commissioned between 01.04.2017 and 30.09.2017 – 12.30%.†
  • For solar PV projects commissioned between 01.10.2017 and 31.03.2018 – 10%.
  • For SPV projects – 10% per annum.
  • Generic levelised tariff – average State Bank of India Marginal Cost of Funds based Lending Rate (one-year tenor) prevalent during the last available six months prior to the effective date of tariff plus 200 basis points.
  • Project specific tariff – minimum of weighted average rate or weighted average of one-year tenor MCLR prevailing during the last available six months prior to the effective date of tariff.

Depreciation
  • 5.28% till the time the loan component of the capital cost is repaid, and balance depreciation spread over the remaining useful life of the project, in straight line method.
  • For solar PV projects commissioned between 01.04.2017 and 30.09.2017 – 5.83% for first 12 years and balance depreciation spread over the remaining useful life of the project, in straight line method.†

Return on Equity

17% per annum on pre-tax basis.

Interest on Working Capital
  • For solar PV projects commissioned between 01.04.2017 and 30.09.2017 – 12.8%.
  • For solar PV projects commissioned between 01.10.2017 and 31.03.2018 – 11%.†
  • For SPV projects – 11% per annum.

  • Generic levelised tariff – average State Bank of India Marginal Cost of Funds based Lending Rate (one-year tenor) prevalent during the last available six months prior to the effective date of tariff plus 300 basis points.

  • Project specific tariff – average of one-year tenor MCLR prevailing during the last available six months prior to the effective date of tariff.

 

OTHER PROVISIONS

 

Tariff structure and design

Generic, levelised, single part tariff for the tariff period.

Subsidy or/and incentives by government
  • For solar PV projects commissioned between 01.04.2017 and 30.09.2017 – nothing is considered except accelerated depreciation.†
  • Any incentive or subsidy provided by the central or state government excluding accelerated depreciation benefit.
  • Only 75% of capital cost shall be considered.

Taxes and Duties

Tariff will include all taxes and duties.

Rebate
  • 2% for payment through Letter of Credit.
  • 1% for payments not through Letter of Credit but within 1 month from the date of presentation of bills.
Late payment surcharge

1.25% per month for actual number of days, for payment of bills beyond a period of 60 days from the date of billing.

Links

http://hperc.org/?page_id=172

http://hperc.org/?page_id=160

References

http://new1.hperc.org/File1/freregu17.pdf

http://hperc.org/File/finalsolar2018.pdf

http://hperc.org/File/SM70-2018.pdf

 

About Portal

‘All About Renewables’ aims to bring about a change in the way we ‘look and search’ for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

(020) 26613855
(020) 26613832