Download Home Back

Haryana Tariff Determination of Renewable Energy Sources, Renewable Purchase Obligation and Renewable Energy Certificate Regulation, 2017, 2nd Amendment

HIGHLIGHTS

 

Tariff Period

  • Generally corresponding to project life or period provided in the PPA.
  • Tariff period: 12 months from COD thereafter on a year-to-year basis.

Control Period

From FY 2017-18 to FY 2020-21.

Useful Life of a Plant

Technology

No. of Years

Non-fossil fuel-based co-generation, Biomass, Municipal Solid Waste to Energy, Biogas

20

Wind, Solar PV, Solar thermal

25

Small Hydro

35

 

Capital Cost for FY 2017-18

Technology

Rs. Crore/MW

Wind

*

Small Hydro below 5 MW

7.79

Small Hydro between 5 MW and 25 MW

7.07

Biomass with water cooled condenser

5.59

Biomass with air cooled condenser

6.00

Biomass using rice straw with water cooled condenser

6.10

Biomass using rice straw with air cooled condenser

6.52

Non- fossil fuel co-generation

4.925

Solar PV polycrystalline

*

Solar PV thin film and rooftop solar PV

*

Solar PV canal-top

*

Solar thermal

*

Biomass gasifier

4.43

Biogas power plant

8.86

MSW based on Rankine cycle

15.00

*Allcapital costs will be project specific

 

Operation and Maintenance (O&M)

Expenses (FY 2017-18)

Technology

O&M Cost (Rs. Crore/MW) for First Year

Wind

Project specific

Small Hydro below 5 MW

0.29

Small Hydro between 5 MW and 25 MW

0.21

Biomass

0.40

Non-fossil fuel co-generation

0.21

Solar PV

project specific

Solar thermal

project specific

Biomass gasifier

0.53

Biogas power plant

0.53

MSW WtE

6.5% of normative capital cost.

O&M cost for FY 2018-19 shall be escalated at percentage specified in Regulation.

Interest Rate on Loans

The normative interest rate shall be considered as the average marginal cost of funds based lending rate (MCLR) (one-year tenor) of SBI prevailing during the last available six months plus a margin of up to 200 basis points, i.e. 2%.

Depreciation

Rate for the first 13 years of the tariff period shall be 5.38% per annum and the remaining depreciation shall be spread over the residual useful life of the project from the 14th year onwards.

Return on Equity

  • 14% per annum on normative equity capital.
  • MAT/Corporate tax shall be separately invoiced.

Interest on Working Capital

Interest on working capital, for the purpose of tariff determination, shall be computed at the average marginal cost of funds based lending rate (MCLR) (one-year tenor) of SBI prevailing during the last available six months plus an appropriate margin not exceeding 200 basis points, i.e. 2%.

Renewable Purchase Obligation (RPO)

Year

Minimum Quantum of Purchase (in %) excluding Hydro

Solar

Non-solar

Total

2016-17

1.00

2.75

3.75

2017-18

2.75

2.75

5.25

2018-19

4.00

3.00

7.00

2019-20

5.50

3.00

8.00

2020-21

7.00

3.00

10.00

2021-22

8.00

3.00

11.00

  • RPO for fossil fuel based CPP of capacity 5 MW and above installed after FY 2018-19 is fixed to RPO target of commissioning year.
  • Obligation to purchase renewable energy shall be inclusive of purchase of renewable energy already being made by obligated entity.
  • Renewable energy purchase under power purchase agreement already entered into shall continue to be made until its validity even if the total renewable energy purchase exceeds RPO.

Obligated Entities

Distribution licensees, captive users and long term open access consumers.

 

Ways to Meet RPO

 

Through purchase of renewable energy or Renewable Energy Certificates or a combination thereof.

  • Solar and non-solar purchase obligations shall be fulfilled by purchase of solar and non-solar certificates, respectively.
  • Certificates purchased shall be submitted to the Commission by the obligated entity as per detailed procedure issued by the Central Agency.

 

OTHER PROVISIONS

 

Tariff Structure and Design

  • Single-part tariff — Return on equity, Interest, O&M etc.
  • Generic tariff — Levelised tariff for entire tariff period.

 

Despatch Principles

“MUST RUN” — All renewable energy plants, except biomass, with capacity of 10 MW and above and non-fossil fuel based co-generation plants.

 

Subsidy or/and Incentives by Government

Any incentive or subsidy provided by the Central or State government.

 

Rebate

  • 2% — for payment through letter of credit.
  • 1% — for payments not through letter of credit but made within 1 month from the date of presentation of bills.

 

Late Payment Surcharge

1.25% per month for payment beyond 60 days from the date of billing.

 

State Agency

Haryana Renewable Energy Development Agency (HAREDA).

 

Effect of Default

  • The Commission may direct obligated entities who fail to fulfill obligation and do not purchase certificates, to deposit an amount into a separate fund to be created and maintained by the obligated entity.
  • The amount to be deposited shall be determined based on the shortfall in RPO and forbearance price.

 

Banking of RE

  • Banking charges + T&D losses.
  • Priority for settlement of wheeled energy at consumer end:
    • RE generator
    • Captive power
    • Banked energy
    • OA power through exchange
    • DISCOM power

Wheeling ,T&D Charges and Cross Subsidy Surcharge

  • Exemption for captive solar plants installed until 13 February 2019.
  • No exemption to IPP/generators for third party sale.

Links

 

References

https://herc.gov.in/writereaddata/pdf/r20180724.pdf

https://herc.gov.in/writereaddata/pdf/r20180827.pdf

https://herc.gov.in/writereaddata/pdf/r20190614.pdf

 

 

 

 

About Portal

‘All About Renewables’ aims to bring about a change in the way we ‘look and search’ for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

(020) 26613855
(020) 26613832