Download Home Back

Arunachal Pradesh Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulation – 2018 (Consolidated)

HIGHLIGHTS

 

Tariff Period

Technology

No. of Years

Municipal solid waste (MSW) and refuse derived fuel (RDF) based power

20

Wind, solar PV

25

Small hydro

35

 

Control Period

3 years, of which the first year shall be FY 2018-19.

Useful Life of a Plant

Technology

No. of Years

Municipal solid waste (MSW) and refused derived fuel (RDF) based power

20

Wind, solar PV

25

Small hydro

35

 

Tariff

Generic tariff for small hydro projects (SHP) FY 2018-19:

 

Capacity

Levelised Cost (Rs./kWh)

Below 500 kW

6.48

500 kW-1 MW

5.84

Project-specific tariff shall be determined in the following cases:

  • Small hydro projects (1 MW to 25 MW).
  • For renewable energy projects which have been commissioned before 31 March 2017 without a power purchase agreement, the project’s tariff shall be determined on an annual basis.
  • Solar PV.
  • Wind energy.
  • MSW and RDF based projects with Rankine cycle technology.
  • Hybrid projects approved by MNRE.
  • Any other new renewable energy technologies approved by MNRE.

 

Financial and operational norms specified in the regulations will be ceiling norms.

 

Capital Cost

All capital costs are for FY 2018-19, and the same for subsequent years are determined using indexation formula given in Regulations.

Technology

Capital Cost (Rs.Lakh/kW)

Wind

Project-specific

SHP - below 500 kW

1.4

SHP – from 500 kW to below 1000 kW

1.2

Solar PV

Project-specific

MSW/RDF

Project-specific

 

Capacity Utilization Factor

Technology

CUF

Wind

Annual Mean Wind Power Density (w/m2) at 100 meters hub-height

CUF

Up to 220

22%

221-275

24%

276-330

28%

331-440

33%

>440

35%

Small hydro*

45%

Solar PV

    19%**

MSW/RDF

Stage

MSW

RDF

During stabilization***

65%

65%

During the remaining period of the first year(after stabilization)

65%

65%

From 2nd year onwards

75%

80%

*Normative CUF is net of free power, if any, to the home state.

**The APERC may deviate from the norm in case of project specific tariff.

***The stabilization period shall not be more than 6 months from the date of commissioning of the project.

Auxiliary Consumption

Technology

Auxiliary Consumption

Small hydro

1%

Solar PV

        0.25%*

MSW/RDF

   15%

*The APERC may deviate from the norms in case of project-specific tariff determination.

 

Operation and Maintenance (O&M)Expenses

Technology

O&M Cost

(Rs.Lakh/MW) for FY 2018-19

Wind

Project-specific

Hydro power below 5 MW

40.24

Hydro power 5 MW - 25 MW

30.17

Solar PV

Project-specific

MSW/RDF

Project-specific

O&M cost is escalated at 5.72% per annum over the tariff period.

Interest Rate on Loans

  • Average State Bank of India marginal cost of funds based lending rate (one-year tenor) prevalent during the last available six months plus 200 basis points.
  • For SHP, the interest on loan is calculated at 10.51%.

Depreciation

  • 5.28% for the first 13 years and the remaining depreciation is spread over the residual useful life of the project taking 10% of the project cost as the salvage value of the project.
  • SHP rate of depreciation is 5.28% for 13 years and 1.425% for the remaining life of the project.

Return on Equity

14% to be grossed up by the prevailing minimum alternate tax as on 1 April of the previous year for the entire useful life of the project.

Interest on Working Capital

Average State Bank of India marginal cost of funds based lending rate (one-year tenor) prevalent during the last available six months plus 300 basis points.

Station Heat Rate (only for MSW/RDF Projects)

4200 kCal/kWh.

Calorific Value (only for RDF)

2500 kCal/kg.

Fuel Cost

RDF – Rs.1800/MT for FY 2018-19 to be escalated at 5% per annum.

MSW – No fuel cost.

 

 

   

OTHER PROVISIONS

 

Tariff Structure and Design

Generic or project specific:

  • Levelised
  • Single part tariff for technologies not using fuel.
  • Single part with fixed cost and fuel cost component for technologies that are using fuel. 

Despatch Principles

  • All renewable energy power plants shall be treated as ‘MUST RUN’ power plants.
  • Scheduling of wind and solar energy shall be governed by:
    • Arunachal Pradesh State Electricity Grid Code as amended from time to time.
    • Central Electricity Regulatory Commission (Indian Electricity Grid Code) (Third Amendment) Regulations, 2015 as amended from time to time.
    • Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) (Second Amendment) Regulations, 2015 as amended from time to time.

Subsidy or/and Incentives by Government

Any incentive or subsidy provided by the central or state government including accelerated depreciation benefit would be taken into consideration for determination of tariff.

Taxes and Duties

As pass-through on actual incurred basis.

Rebate

  • 2% - for payment through Letter of Credit.
  • 1% - for payment not through Letter of Credit but within 1 month from the date of presentation of bills.

Late Payment Surcharge

1.25% per month for payment of bills beyond a period of 60 days from the date of billing.

Links

http://www.apserc.nic.in/index.html

References

http://www.apserc.nic.in/pdf/199.%20EOG.%20No.%20199.%20APSERC%20(2018).pdf

Generic Tariff order 2019-20

http://www.apserc.nic.in/pdf/Generic%20Tariff%20Order%202019-20-%20signed%20copy.pdf

About Portal

‘All About Renewables’ aims to bring about a change in the way we ‘look and search’ for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

(020) 26613855
(020) 26613832