Download Home Back

Renewable Energy Policy – 2018 for U.T. of Dadra Nagar Haveli

HIGHLIGHTS

 

Nodal Agency

Dadra Nagar Haveli Power Distribution Corporation Limited (DNHPDCL).

Policy Period               

  • From the DOI till policy modification or suspension.

Eligible Entities

  • Any individual, company or body corporate or association or body of individuals, whether incorporated or not, or artificial juridical person, for the purpose of captive use and/or for selling of electricity, in accordance with the Electricity Act, 2003.

Policy Goals

To achieve 500 MW of solar power generation by 2022  and yearly targets [A1] as:

  • FY 18-19 - 110 MW
  • FY 19-20 - 120 MW
  • FY 20-21 - 130 MW
  • FY 21-22 - 140 MW
  • All govt. buildings will be covered under solar rooftop.
  • HT companies shall install solar project of 5% of their contract demand.

Power Evacuation

DNHPDCL will facilitate the evacuation:

  • LT - after net metering point onwards.
  • HT/EHT - at pooling station (66/11 kV or 220/66 kV).
  • Outside U.T. -220 kV s[A2] ubstation of DNHPDCL.

Incentives

  • Exemption to OA developers and beneficiaries in associated charges and restrictions.

Subsidy to domestic consumers in solar PV projects and will be released in three steps:

  • 1 kWp> [A3] [A4] Rs.10,000
  • 2 kWp> Rs.20,000
  • 3 kWp> Rs.30,000
  • 4 kWp> Rs.40,000
  • 5 kWp> Rs.50,000

Subsidy from the union territory’s administration does not restrict prosumers from availing benefits from the Central Govt./MNRE.

 

 

 

OTHER PROVISIONS

 

Objective

  • Promotion of RE generation within the UT.
  • Self-sustainability in meeting RPO by 2022.
  • Encouraging private sector participation.
  • Creating skilled manpower and employment.
  • Increasing decentralized distribution to reduce T&D losses.
  • Encouraging the development of RE industry in the UT.

Empanelment of EPC Contractor

  • EPC contractors should register with DNHPDCL and projects will be executed by the empanelled EPC contractors.
  • EPC contractor shall deposit 10% of contract value with DNHPDCL for 5 years as a refundable performance-based security deposit.

Grid-connectivity, Safety and Billing Cycle

Only grid-connected solar plants qualify under this policy:

  • Up to 10 kW - single phase 230 V.
  • More than 10 kW and to up to 100 kW - 3 phase 400 V.
  • Above 100 kW to up to 4 MWp- 11 kV.
  • Beyond 4 MWp- 66 kV.
  • Only solar RPO is available.
  • Group net-metering policy is allowed.

 

Billing Cycle

  • Balance settlement method for prosumers.
  • 6-monthly settlement period, from 1st April to 30th September and from 1st October to 31st March.
  • Producer and prosumers will be exempted from charges with respect to energy banking, wheeling, line losses and cross-subsidy.

Commercial Settlement

  • The power generated will be purchased by DNHPDCL for 25 years as per power procurement rates.

Sale of Energy

  • To consumers, utilities, within the UT or outside it, or to DNHPDCL. For sale to the third party, the developer will not be allowed to sign PPAs with DNHPDCL.[A5] 

Technical Compliance

Only ±5% tolerance is allowed in the rated capacity of solar projects.

Standard

  • Only MNRE approved technology will be connected to the grid for solar projects.

Metering

  • Online monitoring and data acquisition at the inverter and at the bi-directional meter.
  • Prosumers or producers shall arrange [A6] for such meters themselves.

Implementation Period of Projects

Up to 25 kW per location

1 month

Above 25 kW and to up to 100 kW

2 months

Up to 500 kW

3 months

Up to 5 MW

6 months

Above 5 MW

12 months

Single Window Clearance System

  • Facilitation in approval, clearances, permissions and consents related to policy.
  • Ensuring all government orders pertaining to this policy are followed.
  • Ensuring timely provision for evacuation infrastructure.

Links

https://www.dnhpdcl.in/

References

https://www.dnhpdcl.in/Download/SolarGazette.pdf

About Portal

‘All About Renewables’ aims to bring about a change in the way we ‘look and search’ for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

(020) 26613855
(020) 26613832